Process a Planned Production Order in Microsoft Dynamics 365 Supply Chain Management

Process a Planned Production Order

Question

You are the production scheduler at a manufacturing company.

The company is not using advanced warehousing.

You have firmed a planned production order from master planning.

The order is ready to be processed.

You now need to process the order in production control.

What should you do first?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

As the production scheduler, your responsibility is to ensure that production orders are processed efficiently and effectively to meet the production requirements of the company. When a planned production order has been firmed in master planning, it means that the production order has been finalized and is ready to be processed. However, before you can start processing the order in production control, there are some necessary steps you should take first.

The first step you should take when processing a production order in production control is to estimate the order. This involves determining the amount of time, resources, and materials that will be required to complete the production order. Estimating the order helps to ensure that the necessary resources are available and that the production order can be completed within the required timeframe.

Once you have estimated the order, the next step is to schedule the order. Scheduling involves determining the start and end dates for each operation required to complete the production order. Scheduling helps to ensure that resources are allocated effectively and that production orders are completed on time.

After you have scheduled the production order, you can then start the order. Starting the order involves releasing the production order to the shop floor, which allows the workers to begin working on the order.

Finally, once the production order has been completed, you can report the order as finished. This involves updating the production order status in the system and closing the order.

In summary, the correct answer to the question is C. Schedule the order. This is the first step you should take when processing a production order in production control. After scheduling the order, you can then start the order, report the order as finished once it is completed, and estimate the order before scheduling it.