Project Management: Identifying Gaps in Departmental Assignments

Project Planning Oversight: Potential Missed Elements

Question

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it.

Which of the following were MOST likely missed during project planning?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

The correct answer to this question is B. Resource analysis and Gantt chart.

Explanation:

Resource analysis and Gantt chart are key components of project planning. The purpose of resource analysis is to determine the resources required to complete the project, including personnel, materials, and equipment. The project manager must identify the necessary resources and ensure they are available when needed. If the project team does not have enough resources, it can delay or derail the project.

A Gantt chart is a visual representation of a project schedule. It shows the start and end dates of each task in the project, as well as their dependencies. The Gantt chart allows the project manager to see how the project is progressing, identify any delays, and adjust the schedule as needed.

If a department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it, it is likely that the project manager did not do a thorough resource analysis or create a detailed Gantt chart. Without these planning tools, the project manager may not have allocated enough resources or established a realistic schedule.

The other options, A, C, and D, are also important components of project planning, but they are less likely to be the cause of the issues with the project in this scenario. An issue log and process diagram are useful for identifying and managing project risks and issues. Stakeholder analysis and communication plan are important for managing project stakeholders and ensuring effective communication. A scatter chart and scope analysis are helpful for understanding the scope of the project and identifying any areas of risk or opportunity. However, these items would not directly impact the project's resource allocation or schedule in the same way that a resource analysis and Gantt chart would.