CompTIA Project+ Exam: Determining Root Cause of an Issue

Determining Root Cause of an Issue

Question

Which of the following tools would a project manager use to determine the root cause of an issue?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

The tool that a project manager would use to determine the root cause of an issue is the Ishikawa diagram (also known as a fishbone diagram or cause-and-effect diagram).

An Ishikawa diagram is a graphical tool that helps to identify and analyze the potential causes of a particular problem or issue. The diagram takes the form of a fishbone, with the "head" representing the problem or issue, and the "bones" representing the possible causes or factors that may contribute to the problem.

To create an Ishikawa diagram, the project manager would start by identifying the problem or issue at the head of the diagram. They would then work backwards, brainstorming and identifying potential causes and factors that may contribute to the problem, and attaching them to the appropriate bone of the diagram.

Once all potential causes have been identified, the project manager can then analyze the diagram to determine which factors are most likely to be the root cause of the problem. By visually organizing and prioritizing potential causes, the Ishikawa diagram helps the project manager to focus their efforts on the most likely causes of the issue, and develop a plan to address them.

The other tools listed in the question are also useful for project management, but are not specifically designed to determine the root cause of an issue.

  • A Pareto chart is a bar graph that shows the relative frequency or size of problems in descending order of importance, and is useful for identifying the most common problems or issues.
  • A histogram is a graphical representation of data that shows the frequency distribution of a variable, and is useful for analyzing patterns in data.
  • Monte Carlo analysis is a statistical technique that uses probability distributions to simulate the possible outcomes of a project or process, and is useful for predicting project outcomes and assessing risks.