PK0-004 Exam: Calculate Schedule Variance for CompTIA Project+

Schedule Variance Calculation - PK0-004 Exam Answer

Question

The design activity of a project has the following cost attributes: PV = 100,000 - EV = 20,000 - AC = 90,000 - Based on this scenario, calculate the schedule variance.

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

In project management, Schedule Variance (SV) is a measure of the difference between the Planned Value (PV) and the Earned Value (EV). The formula for Schedule Variance (SV) is:

SV = EV - PV

Where:

  • PV is the planned value (also known as Budgeted Cost of Work Scheduled or BCWS), which represents the authorized budget assigned to the scheduled work for an activity or a work breakdown structure component.
  • EV is the earned value (also known as Budgeted Cost of Work Performed or BCWP), which represents the value of the work actually completed.
  • AC is the actual cost (also known as Actual Cost of Work Performed or ACWP), which represents the actual cost incurred in completing the work.

Given:

  • PV = 100,000
  • EV = 20,000
  • AC = 90,000

We can calculate the Schedule Variance (SV) as:

SV = EV - PV SV = 20,000 - 100,000 SV = -80,000

Therefore, the answer is A. -80,000.

This means that the project is behind schedule by $80,000 as the earned value (EV) is less than the planned value (PV) by $80,000.