Project Status: Examining PK0-004 CompTIA Project+ Question

Project Status: Examining PK0-004 CompTIA Project+ Question

Question

The project schedule performance index is 1.1, and the cost performance index is 0.9

Which of the following describes the project status?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

The project schedule performance index (SPI) is a measure of the project's progress against the schedule baseline. It is calculated by dividing the earned value (EV) by the planned value (PV). If the SPI is greater than 1, it indicates that the project is ahead of schedule, while an SPI of less than 1 indicates that the project is behind schedule. An SPI of 1 indicates that the project is on schedule.

The cost performance index (CPI) is a measure of the project's progress against the budget baseline. It is calculated by dividing the earned value (EV) by the actual cost (AC). If the CPI is greater than 1, it indicates that the project is under budget, while a CPI of less than 1 indicates that the project is over budget. A CPI of 1 indicates that the project is on budget.

Based on the values provided, the project has an SPI of 1.1, indicating that the project is ahead of schedule. The CPI is 0.9, indicating that the project is over budget.

Therefore, the correct answer is A) Ahead of schedule and over budget.