CompTIA Project+: Project Charter Phase

Project Charter Phase

Question

A project manager is working on the project charter.

Which of the following phases does this describe?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

107

The correct answer is A. Initiation.

Explanation:

The project charter is a high-level document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. The project charter is typically developed in the initiation phase of the project life cycle, which is the first phase of project management.

During the initiation phase, the project manager works with stakeholders to define the project objectives, identify the project scope, establish the project team, and develop the project charter. The project charter includes key information such as the project purpose, business case, project objectives, high-level requirements, project risks, and key stakeholders.

The project charter serves as a contract between the project sponsor, stakeholders, and the project team. It establishes the project's scope, objectives, and authority, and provides a framework for the project team to develop the project plan, execute the project work, and monitor and control project progress.

In summary, the development of a project charter is a key activity in the initiation phase of the project life cycle. It sets the foundation for the project and provides the project manager with the necessary authority to manage the project successfully.