Scrum Project Roles

Roles Involved in a Scrum Project

Question

Which of the following are the roles involved in a Scrum project?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

The correct answer is C. Scrum master, product owner, development team.

Explanation:

Scrum is an agile framework for managing and completing complex projects. It is widely used in software development projects but can be applied to any project. The framework involves a set of roles, events, artifacts, and rules.

The roles involved in a Scrum project are:

  1. Scrum Master: The Scrum Master is the facilitator of the Scrum process. Their primary responsibility is to ensure that the Scrum team adheres to the Scrum framework and follows its practices. They also ensure that the team is productive, removes any impediments that prevent the team from achieving its goals, and coach the team to self-organize.

  2. Product Owner: The Product Owner is responsible for maximizing the value of the product and the work of the Development Team. They are the interface between the stakeholders and the Development Team. The Product Owner creates and manages the product backlog, prioritizes the backlog items based on business value, and communicates the vision and goals of the product to the Development Team.

  3. Development Team: The Development Team is responsible for delivering a potentially shippable product increment at the end of each Sprint. The team is self-organizing and cross-functional, meaning it has all the necessary skills to deliver the product increment. The team is accountable for estimating the effort required to deliver the backlog items and delivering them within the Sprint.

Option A is incorrect because there is no role called "quality coach" in Scrum. The Development Team is responsible for the quality of the product increment.

Option B is incorrect because the Business Analyst is not a role in Scrum. The Product Owner is responsible for defining and prioritizing the requirements of the product.

Option D is incorrect because the Project Sponsor is not a role in Scrum. The Product Owner is the single point of accountability for the product and represents the stakeholders' interests.