Question 222 of 350 from exam PK0-004: CompTIA Project+

Question 222 of 350 from exam PK0-004: CompTIA Project+

Question

Tasks B and D start after Task A is completed.

Task C starts after Tasks B and D are completed.

task E starts after Task D is completed.

Task H starts after task B is completed.

Task G starts after Tasks C and H are completed.

Task F starts after Task E is completed.

Following are the durations of all tasks:

Task Duration

ZTanmooo>r

Four weeks
Two weeks
Six weeks
Three weeks
Seven weeks
One week
Two weeks
Nine weeks

Which of the following tasks are on the critical path?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.