CompTIA Project+: Communicating Project Timeline Changes

Communicating Project Timeline Changes

Question

Which of the following job roles is primarily tasked with communicating the project timeline changes?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

93

The job role primarily tasked with communicating the project timeline changes is the Project Manager.

The Project Manager is responsible for planning, executing, monitoring, controlling, and closing a project. As part of this responsibility, the Project Manager must ensure that the project stays on schedule and within budget. They are responsible for creating a project schedule that outlines the tasks, timelines, and dependencies required to complete the project.

When changes occur in the project timeline, the Project Manager is responsible for communicating these changes to the appropriate stakeholders. This includes the project team, the project sponsor, and any other stakeholders who may be impacted by the change.

The Project Scheduler is responsible for creating and maintaining the project schedule, but they are not typically responsible for communicating changes to the schedule. Instead, they work closely with the Project Manager to ensure that the schedule is accurate and up-to-date.

The Project Sponsor is typically a senior executive who provides funding for the project and serves as an advocate for the project within the organization. While they may be informed of changes to the project timeline, they are not typically responsible for communicating these changes to stakeholders.

The Project Coordinator is responsible for supporting the Project Manager and ensuring that project tasks are completed on time and within budget. While they may assist in communicating changes to the project timeline, they are not typically the primary person responsible for this task.

In summary, the Project Manager is the job role primarily tasked with communicating project timeline changes to stakeholders.