Question

An organization wants assurance that the specialty tools necessary for operation will function as intended for a specific minimum time period.

Which of the following documents BEST provides this assurance?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D. E.

D.

The document that best provides assurance that the specialty tools necessary for operation will function as intended for a specific minimum time period is the Warranty.

A Warranty is a guarantee or assurance made by a manufacturer or seller to repair or replace a product within a specific period if it fails to perform as intended. It provides assurance to the customer that the product they are purchasing will work as intended for a specific period of time.

A Purchase Order is a document that is used to request goods or services from a vendor. It outlines the specific items that are being ordered, the price, and the delivery date. It does not provide any assurance regarding the functioning of the tools.

A Non-Disclosure Agreement (NDA) is a legal contract between two parties that outlines confidential material, knowledge, or information that the parties wish to share with one another for certain purposes. It does not provide any assurance regarding the functioning of the tools.

A Request for Proposal (RFP) is a document that is used to solicit proposals from vendors or suppliers for a project or initiative. It outlines the specific requirements of the project, including the scope of work, budget, and timeline. It does not provide any assurance regarding the functioning of the tools.

A Service Level Agreement (SLA) is a contract between a service provider and a customer that outlines the specific services that will be provided, the level of service, and the time frame in which the service will be provided. It does not provide any assurance regarding the functioning of the tools.

Therefore, the Warranty is the document that best provides assurance that the specialty tools necessary for operation will function as intended for a specific minimum time period.