Question

Which of the following documents should be used to provide high-level reporting to key stakeholders?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

325

The document that should be used to provide high-level reporting to key stakeholders is the Dashboard (Option A).

A dashboard is a high-level graphical representation of project performance that shows key performance indicators (KPIs) and provides a visual summary of project progress. Dashboards typically use charts, graphs, and other visual aids to provide a quick overview of project status and performance.

The dashboard is an essential tool for project managers and stakeholders as it enables them to monitor the project's progress in real-time and make informed decisions based on current data. It provides a high-level view of project status and helps to identify potential issues before they become significant problems.

The Communication plan (Option B) is a document that outlines how project communication will be managed and should include details on who will receive communication, how often, and what type of information will be included. It is not used for high-level reporting to key stakeholders.

The Statement of work (Option C) is a document that defines the scope, deliverables, and objectives of a project. It provides details on what needs to be done, how it will be done, and what the project's final outcome will be. It is not used for high-level reporting to key stakeholders.

The Project charter (Option D) is a document that formally authorizes a project and provides the project manager with the authority to allocate resources and make decisions. It defines the project's objectives, scope, and key stakeholders. It is not used for high-level reporting to key stakeholders.

In summary, the document that should be used to provide high-level reporting to key stakeholders is the Dashboard (Option A), which provides a quick and easy-to-understand view of project performance using visual aids such as charts and graphs.