Meeting Triggered by Quality Assurance Discussion | Exam PK0-004

Quality Assurance Meeting Triggers

Question

A meeting has taken place with quality assurance tram members and the project manager.

Which of the following events would MOST likely have triggered the meeting?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

Based on the limited information provided in the question, it is difficult to determine the specific event that would most likely have triggered the meeting. However, we can make some educated guesses based on the options provided.

A. Audit: An audit is a review of a project's processes and deliverables to ensure that they are compliant with industry standards, regulations, and best practices. If an audit were scheduled or if the project team received notice of an upcoming audit, the quality assurance team would likely want to meet with the project manager to ensure that the project is on track and that any potential issues or non-compliances can be addressed.

B. Risk register update: The risk register is a tool used to identify, assess, and manage project risks. If there were significant updates to the risk register, such as the identification of a new high-risk item or the realization of a previously identified risk, the quality assurance team may want to meet with the project manager to discuss how these risks will be mitigated and how they may impact project quality.

C. Task completion: Task completion is a routine event in any project. Unless a specific task had significant implications for project quality, it is unlikely that a meeting between the quality assurance team and the project manager would be triggered by task completion alone.

D. Resource change: A resource change could refer to a change in personnel, equipment, or materials used on the project. If this change had implications for project quality, such as a change in the skill level of personnel or a change in the quality of materials being used, the quality assurance team would likely want to meet with the project manager to ensure that project quality is maintained.

Overall, the best answer depends on the specific context and details of the project. However, based on the limited information provided, options A (audit) and B (risk register update) seem to be the most likely triggers for a meeting between the quality assurance team and the project manager.