Question 331 of 350 from exam PK0-004: CompTIA Project+

Question 331 of 350 from exam PK0-004: CompTIA Project+

Question

The PMO is confused by an entry in the risk register and would like the project manager to provide clarification regarding strategy.

Based on the following entry:

ID

Name

Status

Owner

Strategy

Specific Response

100

Datacenter fire

Risk

Project manager

Avoid

Conduct regular off-site backups

Which of the following should be modified to BEST eliminate confusion?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.